The project started in December 2007 with the installation of the RAC and Oracle Homes. By January the 8-th 3 of the instances that made scope of the project were already ready for UAT. The testing took more than 1,5 months with more than 1500 users from each area involved in the process. The Vector team was assisting the customer onsite in case any issues occurred. Also, by 15th of February all testing was successfully finished. The cutover and the final migration to live was scheduled with a 16 hours downtime and another 8 hours testing from EMAAR's side.
The project finished in April after the last instance was migrated (each instance migration was scheduled according to managerial decision from each department). |